Running the PR Update Project Initiator report

Use this report to update the purchase request Process Initiator in Axiom Capital Tracking.

To run the PR Update Project Initiator report:

  1. In the Cap Track Admin task pane, in the Administration section, click Administrative Utilities > Security Setup, and double-click PR Update Project Initiator.

  2. Refresh the data in the report by doing one of the following:
    • In the Main ribbon tab, in the Workbook Options group, click Refresh Data.

    • Press F9.
  3. To update the Process Initiator for all purchase requests, in the Main ribbon tab, click Save.

  4. At the confirmation prompt, click OK.